November 12, 2026
On October 13, the City of Winter Park held a morning celebration at the corner of Garfield and Park avenues for the end of Phase 1 of the Park Avenue Refresh. In its media alert, the city described that corner as "the southern boundary of Phase 1 improvements." Seven weeks later, on December 3, the Morse Museum will light its Tiffany windows in the northern section of Central Park, near that same intersection.
North of Garfield, the street is finished. South of Garfield, along Central Park, Phase 2 is expected to start in January 2027. Winter Park's three biggest holiday traditions fall between those two phases this year. That makes December 3 to 5 the first holiday weekend on the new north end. It is also the last scheduled one before barricades reach the blocks where the tree, the stage and the parade crowds gather.
Phase 1 started January 20, 2026, and was paid for by the Community Redevelopment Agency. Bungalower reported that this phase cost $2.5 million out of a projected $8.5 million for all three phases. The outlet also called the project the biggest update to Park Avenue's streetscape since the 1996 to 1999 restoration.
Most of the work is easiest to see after dark. According to the city, Phase 1 added:
Bungalower reported that Phase 1 includes 110 custom "smart" light poles that can support LED lighting, Wi-Fi routers and irrigation. The city's September 9 construction update placed the finishing work between Swoope and Garfield avenues. That update covered seasonal plantings in the new pots, new stone caps on the raised brick beds, and Liriope going into the planters. WFTV reported the phase complete on October 14.
In the October media alert, the city wrote that it had finished Phase 1 "before the busy holiday season." The holiday weekend is that busy season.
Each of the three traditions takes place near Garfield Avenue.
| Event | When | Where | Position relative to Phase 1 and Phase 2 |
|---|---|---|---|
| Christmas in the Park, Morse Museum | Thursday, Dec. 3, 6:15 to 8:30 p.m. | Northern Central Park near Garfield and Park avenues | Next to the Phase 1 boundary, on the Central Park side |
| Winter on the Avenue, Winter Park Chamber of Commerce | Friday, Dec. 4, 5 to 9 p.m. | Central Park, with the tree just east of the train station | Inside the Phase 2 frontage |
| 74th Ye Olde Hometown Christmas Parade | Saturday, Dec. 5, 9 to 10:30 a.m. | Park Avenue, from Cole Avenue south, turning at New England Avenue and ending at Pennsylvania Avenue | Travels down Park Avenue past the Central Park blocks |
The Morse Museum's Christmas in the Park is free. The windows light on a signal at 6:15 p.m., the Bach Festival Choir and Brass Ensemble concert ends around 8:00, and the windows stay lit until 8:30. Blankets and lawn chairs can go down starting at 4:00 p.m., after the windows are installed. Tables are not allowed.
The next evening, the Chamber's Winter on the Avenue moves the activity south into the park. The program lists the annual tree lighting, strolling carolers, a Chanukah menorah lighting ceremony, s'mores, snow slides, the holiday art contest winners, children's choirs, Popcorn Flicks in the park, "a snowy surprise," and Santa and Mrs. Claus.
Saturday begins with the pancake breakfast at the Central Park Stage from 7 to 10:30 a.m., according to the Chamber's 2026 event calendar. The 74th parade steps off at 9. The Chamber calls it the oldest continuous holiday parade in Central Florida, with more than 80 participating organizations, including marching bands, police and fire departments, scouting groups and Santa.
Phase 2 runs from Garfield to New England avenues, along Central Park. Bungalower reported in February that the City Commission voted 5-0 to approve a $240,250 design contract with Stringfellow Planning & Design for this segment. The same report noted that the east side of the street has a heavy concentration of restaurants and shops, including Briarpatch, Prato, Tabla Indian Restaurant and Lululemon.
The city's project manager has said this segment is harder than Phase 1. Bungalower quoted communications director and project manager Clarissa Howard:
"Phase 2 is significantly different than Phase 1 due to the number of businesses along the eastern side of Park Avenue and Central Park on the west."
In the same report, Howard said the city plans to keep pedestrian walkways open to each Phase 2 merchant. She also said that because Central Park borders the west side, the work will not interfere with shopping or dining on that side. Phase 2 also takes in the Morse Boulevard and New England Avenue intersections. Howard pointed out that this stretch hosts special events, including the Sidewalk Art Festival, and said the city "will work with event organizers on the type of construction that will be occurring during the event time and how best to accommodate any areas that are within a construction zone."
The design team plans to reuse the elements that went in north of Garfield. Bungalower quoted Alex Stringfellow: "We have the kit of parts, and this Phase will allow us to deploy that design in the most impactful way." The team plans to study the Morse Boulevard intersection, the Rose Garden entry and the edges of Central Park. It is also looking at bulb-outs that enlarge the tree beds around established oaks and a possible wider sidewalk near Briarpatch. The city's June Phase 2 concept presentation adds a Central Park entry feature, a bus-stop building, handrails, new trees and new light poles.
This year's lighting, Friday program and parade therefore take place on the Central Park frontage as it has looked since the late 1990s restoration. The north end, about a block away, already has the new poles, planters and oaks that are planned for this stretch.
The Morse Museum lists street parking, the museum's own lot and several City of Winter Park lots for Christmas in the Park. It links to a printable downtown parking map on the city's site. The museum also notes the event is a short walk from the Winter Park SunRail station.
For road closures, last year's notice gives the general pattern. In its December 1, 2025 notice, the city closed Park Avenue between Canton Avenue and Morse Boulevard for Christmas in the Park. It closed Park Avenue between West Canton Avenue and Lyman Avenue from the evening before the parade through the parade itself. The city's newsroom posts each year's closures, and the 2026 notice will set the exact blocks and hours for this weekend.
After the weekend, the Park Avenue Refresh project page is where the city posts Phase 2 updates. Phase 3, from New England south to Fairbanks Avenue, is expected to begin in 2028.
Updates to a street like Park Avenue affect how buyers see a Winter Park address and how sellers present one. At CC Luxury Group, Crystal Canina follows these changes block by block. If you would like to talk through how the Park Avenue Refresh affects a home you own or are considering near downtown, Schedule a Complimentary Luxury Consultation.
With over 20 years of knowledge, and $150 Million in real estate sold representing hundreds of transaction sides you can count on Crystal's experience. It is our goal as your full-service real estate consultants specializing in the Central Florida area, to provide you with superior service at all times.